[CKAN-support] Queensland SSQ penetration testing forms for Rackspace

Joel Rebello joel.rebello at okfn.org
Mon Feb 25 07:54:43 UTC 2013


Hey Lawrence,

 We've created a ticket with Rackspace support, will get back to you
as soon as we get a response.


Regards,
Joel Rebello

On Mon, Feb 25, 2013 at 11:02 AM, Lawrence Howson <lawrence at xvt.com.au> wrote:
> Hi again Joel,
>
> Queensland Government have just advised there will be a delay in their start of the penetration testing. This is now scheduled to commence Monday 4th March and last 7 days. If you could let Rackspace, that would be appreciated.
>
> They have also asked if there is a direct technical contact at Rackspace who can be emailed by the consultants conducting the tests. I believe this is to get in contact with them if they should break anything during the testing process. Its a mandatory requirement from their consultants. If you could advise, that would be great.
>
> Best regards,
>
> Lawrence
>
> On 23/02/2013, at 3:22 AM, Joel Rebello <joel.rebello at okfn.org> wrote:
>
>> Hey Lawrence,
>>
>> We've just got confirmation from Rackspace, we're good to go with the
>> testing any day from today 22nd Feb :)
>>
>>
>> Regards,
>> Joel Rebello
>>
>> On Wed, Feb 20, 2013 at 11:36 AM, Lawrence Howson <lawrence at xvt.com.au> wrote:
>>> Hi Darwin and Joel,
>>>
>>> Thanks for the update. Look forward to receiving a firm date from you, as
>>> Queensland SSQ are keen to expedite this.
>>>
>>> Thanks,
>>>
>>> Lawrence
>>>
>>> On 19/02/2013, at 10:10 PM, Darwin Peltan <darwin.peltan at okfn.org> wrote:
>>>
>>> Hi Lawrence,
>>>
>>> We're speaking to Rackspace about this at the moment but I think they will
>>> need more notice than 20th of Feb. Joel will update you.
>>>
>>> Best,
>>>
>>> Darwin
>>>
>>> Darwin Peltan
>>> Project Manager
>>>
>>> The Open Knowledge Foundation
>>> http://www.okfn.org
>>>
>>> Skype: darwinp
>>> Twitter: @darwin
>>>
>>>
>>> On 18 February 2013 00:46, Lawrence Howson <lawrence at xvt.com.au> wrote:
>>>>
>>>> Hi Joel and Gavin,
>>>>
>>>> Queensland SSQ have sent through the partially completed form for
>>>> Rackspace for scheduling the penetration testing.
>>>>
>>>> The document stipulates that it must be with Rack Space 7 days prior to
>>>> the proposed testing. However, they would like to begin testing next week
>>>> starting 20 Feb if not sooner, and wonder if you might be able to negotiate
>>>> an earlier start date? Can you please let me know by Monday if this is
>>>> possible?
>>>>
>>>> Thanks,
>>>>
>>>> Lawrence
>>>>
>>>> ________________________________
>>>> This email and any files transmitted with it is confidential and intended
>>>> solely for the use of the addressee. The unauthorised use, dissemination,
>>>> forwarding, printing or copying of this communication is strictly
>>>> prohibited. If you have received this communication in error please notify
>>>> us immediately by reply email and destroy this communication. Any views and
>>>> opinions presented in this email are solely those of the author and do not
>>>> necessarily represent the views of XVT Solutions. The recipient should check
>>>> this email and any attachments for viruses. XVT Solutions accepts no
>>>> liability for the content of this email, and any damage caused by any
>>>> viruses that could potentially be transmitted through this email.
>>>>
>>>> _______________________________________________
>>>> CKAN-support mailing list
>>>> CKAN-support at lists.okfn.org
>>>> http://lists.okfn.org/mailman/listinfo/ckan-support
>>>>
>>>
>>>
>>>
>>> _______________________________________________
>>> CKAN-support mailing list
>>> CKAN-support at lists.okfn.org
>>> http://lists.okfn.org/mailman/listinfo/ckan-support
>>>
>




More information about the ckan-support mailing list