Just to say that we decided not to attempt this ticket within the
current iteration:
http://project.knowledgeforge.net/domainmodel/trac/ticket/3
Best wishes,
John.
Rufus Pollock wrote:
> === Next iteration ===
>
> * John Bywater will be allocating 2 weeks to this iteration.
> * Rufus Pollock will be allocating 1-2 weeks to this iteration.
> * Work will be on domainmodel and ckan.
> * We will be using trac to schedule work on these projects.
>
> For domainmodel this is milestone1:
>
> <http://project.knowledgeforge.net/domainmodel/trac/milestone/milestone1>
>
> For ckan this is milestone2:
>
> <http://project.knowledgeforge.net/ckan/trac/milestone/milestone2>
>
> First priority will be domainmodel since everything else depends on this.
>
> For CKAN there is still some work to reallocate (semi-)uncompleted
> items from milestone1 into milestone2 (or even milestone3).
>